Westonci.ca is the ultimate Q&A platform, offering detailed and reliable answers from a knowledgeable community. Join our platform to get reliable answers to your questions from a knowledgeable community of experts. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

it takes 10 workers 10 days to paint 10 houses. How many houses can five workers paint in five days?

Sagot :

AL2006
10 workers paint 10 houses in 10 days.

So . . . 10 workers paint 1 house a day.

So . . . 5 workers paint 1/2 house per day.

So . . . The same 5 workers can paint (5 x 1/2) = 2 and 1/2 houses in 5 days.