Welcome to Westonci.ca, where your questions are met with accurate answers from a community of experts and enthusiasts. Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Hayden is a manager at a landscaping company. He has 3 workers to
landscape an entire park, Cody, Kaitlyn, and Joseph. Cody can complete
the project in 8 hours. Kaitlyn can complete the project in 6 hours.
Joseph is new, so no one knows how long it will take him.

Hayden
assigns all of them to complete the park together. Explain to Hayden
how this project can tell him how long it would take Joseph to complete
the project if he worked by himself. Use complete sentences.