Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Get accurate and detailed answers to your questions from a dedicated community of experts on our Q&A platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Sagot :

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.