Looking for trustworthy answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Project C: What is the total crash cost for crashing the following project by FOUR days? Activity Immediate Normal Time Crash Time Normal Cost Crash Cost CC in $ 8000 7000 Predecessor NT in days CT in days NC in 7000 5000 9000 | A. D B,C 5000 3000 2000 4000 5000 E,F 7000 a. $4000 b. $1500 c. $3000 d. $2500

Sagot :

Answer: c. $3000

Explanation:

Crashing Critical Part A, B, D, F, G.

Crash A by 2 days would increase cost from $7,000 to $8,000

= 8,000 - 7,000

= $1,000

Crash B by 2 days would increase cost from $5,000 to $7,000

= 7,000 - 5,000

= $2,000

Crash cost of four days:

= 1,000 + 2,000

= $3,000