Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Discover in-depth solutions to your questions from a wide range of experts on our user-friendly Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

Project C: What is the total crash cost for crashing the following project by FOUR days? Activity Immediate Normal Time Crash Time Normal Cost Crash Cost CC in $ 8000 7000 Predecessor NT in days CT in days NC in 7000 5000 9000 | A. D B,C 5000 3000 2000 4000 5000 E,F 7000 a. $4000 b. $1500 c. $3000 d. $2500

Sagot :

Answer: c. $3000

Explanation:

Crashing Critical Part A, B, D, F, G.

Crash A by 2 days would increase cost from $7,000 to $8,000

= 8,000 - 7,000

= $1,000

Crash B by 2 days would increase cost from $5,000 to $7,000

= 7,000 - 5,000

= $2,000

Crash cost of four days:

= 1,000 + 2,000

= $3,000

View image Parrain
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.