Westonci.ca is the premier destination for reliable answers to your questions, brought to you by a community of experts. Join our platform to get reliable answers to your questions from a knowledgeable community of experts. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
Answer:
Week 1 =3.03
Week 2 =2.99
Week 3=2.9
Week 4=2.83
Step-by-step explanation:
Computation for the multifactor productivity measure for each of the weeks shown for production of chocolate bars.
Using this formula
Week Multifactor productivity measure = (Output / Total Cost)
Where:
Output represent Quantity produced
Total cost represent Labor cost + Material cost + Overhead
Let plug in the formula
Week 1= 30,000/(40*12*6)+[(40*12*6)1.5]+(450*6)
Week 1 =30,000/(2,880)+(2,880*1.5)+2,700
Week 1 =30,000/(2,880+4,320+2,700)
Week 1=30,000/9,900
Week 1 =3.03
Week 2= 33,600/(40*12*7)+[(40*12*7)1.5]+(470*6)
Week 2 =33,600/(3,360)+(3,360*1.5)+2,820
Week 2=33,600/(3,360+5,040+2,820)
Week 2=33,600/11,220
Week 2 =2.99
Week 3= 32,200/(40*12*7)+[(40*12*7)1.5]+(460*6)
Week 3 =32,200/(3,360)+(3,360*1.5)+2,760
Week 3=32,200/(3,360+5,040+2,760)
Week 3=32,200/11,160
Week 3=2.9
Week 4= 35,400/(40*12*8)+[(40*12*8)1.5]+(480*6)
Week 4 =35,400/(3,840)+(3,840*1.5)+2,880
Week 4=35,400/(3,840+5,760+2,880)
Week 4=35,400/12,480
Week 4=2.83
Therefore the multifactor productivity measure for each of the weeks shown for production of chocolate bars is :
Week 1 =3.03
Week 2 =2.99
Week 3=2.9
Week 4=2.83
Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.