Westonci.ca offers fast, accurate answers to your questions. Join our community and get the insights you need now. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer:
Week 1 =3.03
Week 2 =2.99
Week 3=2.9
Week 4=2.83
Step-by-step explanation:
Computation for the multifactor productivity measure for each of the weeks shown for production of chocolate bars.
Using this formula
Week Multifactor productivity measure = (Output / Total Cost)
Where:
Output represent Quantity produced
Total cost represent Labor cost + Material cost + Overhead
Let plug in the formula
Week 1= 30,000/(40*12*6)+[(40*12*6)1.5]+(450*6)
Week 1 =30,000/(2,880)+(2,880*1.5)+2,700
Week 1 =30,000/(2,880+4,320+2,700)
Week 1=30,000/9,900
Week 1 =3.03
Week 2= 33,600/(40*12*7)+[(40*12*7)1.5]+(470*6)
Week 2 =33,600/(3,360)+(3,360*1.5)+2,820
Week 2=33,600/(3,360+5,040+2,820)
Week 2=33,600/11,220
Week 2 =2.99
Week 3= 32,200/(40*12*7)+[(40*12*7)1.5]+(460*6)
Week 3 =32,200/(3,360)+(3,360*1.5)+2,760
Week 3=32,200/(3,360+5,040+2,760)
Week 3=32,200/11,160
Week 3=2.9
Week 4= 35,400/(40*12*8)+[(40*12*8)1.5]+(480*6)
Week 4 =35,400/(3,840)+(3,840*1.5)+2,880
Week 4=35,400/(3,840+5,760+2,880)
Week 4=35,400/12,480
Week 4=2.83
Therefore the multifactor productivity measure for each of the weeks shown for production of chocolate bars is :
Week 1 =3.03
Week 2 =2.99
Week 3=2.9
Week 4=2.83
Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.