Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Get quick and reliable solutions to your questions from a community of experienced professionals on our platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
Week 1 =3.03
Week 2 =2.99
Week 3=2.9
Week 4=2.83
Step-by-step explanation:
Computation for the multifactor productivity measure for each of the weeks shown for production of chocolate bars.
Using this formula
Week Multifactor productivity measure = (Output / Total Cost)
Where:
Output represent Quantity produced
Total cost represent Labor cost + Material cost + Overhead
Let plug in the formula
Week 1= 30,000/(40*12*6)+[(40*12*6)1.5]+(450*6)
Week 1 =30,000/(2,880)+(2,880*1.5)+2,700
Week 1 =30,000/(2,880+4,320+2,700)
Week 1=30,000/9,900
Week 1 =3.03
Week 2= 33,600/(40*12*7)+[(40*12*7)1.5]+(470*6)
Week 2 =33,600/(3,360)+(3,360*1.5)+2,820
Week 2=33,600/(3,360+5,040+2,820)
Week 2=33,600/11,220
Week 2 =2.99
Week 3= 32,200/(40*12*7)+[(40*12*7)1.5]+(460*6)
Week 3 =32,200/(3,360)+(3,360*1.5)+2,760
Week 3=32,200/(3,360+5,040+2,760)
Week 3=32,200/11,160
Week 3=2.9
Week 4= 35,400/(40*12*8)+[(40*12*8)1.5]+(480*6)
Week 4 =35,400/(3,840)+(3,840*1.5)+2,880
Week 4=35,400/(3,840+5,760+2,880)
Week 4=35,400/12,480
Week 4=2.83
Therefore the multifactor productivity measure for each of the weeks shown for production of chocolate bars is :
Week 1 =3.03
Week 2 =2.99
Week 3=2.9
Week 4=2.83
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.