Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Get detailed answers to your questions from a community of experts dedicated to providing accurate information. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

It takes 5 men 12 days ro complete a job how many days does it take 3 men to complete the job

Sagot :

Answer:

5=12

3=? then Criss cross it and you will get 12*3 divided by 5 then you get 7.2

so the answer will be 7 days