Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Get quick and reliable solutions to your questions from knowledgeable professionals on our comprehensive Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

It takes 5 men 12 days ro complete a job how many days does it take 3 men to complete the job

Sagot :

Answer:

5=12

3=? then Criss cross it and you will get 12*3 divided by 5 then you get 7.2

so the answer will be 7 days

We hope this was helpful. Please come back whenever you need more information or answers to your queries. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thank you for choosing Westonci.ca as your information source. We look forward to your next visit.