At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Connect with a community of experts ready to provide precise solutions to your questions on our user-friendly Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer:
b. 17 weeks.
Explanation:
From the table given:
Activity Immediate Predecessor(s) Activity Time in weeks
A None 1
B None 1
C A 4
D B 5
E C,D 5
F E 3
G F 2
Suppose activity was delayed for two weeks, the critical path afte the delay would be combination of (A-C-E-F-G)
= 1 + 6 + 5 + 3 + 2
= 17 weeks
We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.