Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

Jude is in charge of the advertising program for the boston red sox baseball team during their spring training in fort myers floida. he has defined the advertising program asa project with the following characteristics. the goal is to fill all stadium seats during the spring training season.
Activity Immediate Predecessor(s) Activity Time in weeks
A None 1
B None 1
C A 4
D B 5
E C,D 5
F E 3
G F 2
If activity is delayed by 2 weeks, then the revised earliest project completion time is_______.
a. 16 weeks.
b. 17 weeks.
c. 18 weeks.
d. 19 weeks.


Sagot :

Answer:

b. 17 weeks.

Explanation:

From the table given:

Activity         Immediate Predecessor(s)      Activity Time in weeks

A                     None                                                  1    

B                     None                                                  1  

C                       A                                                      4

D                       B                                                      5

E                       C,D                                                   5  

F                        E                                                      3

G                        F                                                      2

Suppose activity was delayed for two weeks, the critical path afte the delay would be combination of (A-C-E-F-G)

= 1 + 6 + 5 + 3 + 2

= 17 weeks