Westonci.ca is the premier destination for reliable answers to your questions, brought to you by a community of experts. Experience the ease of finding reliable answers to your questions from a vast community of knowledgeable experts. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

Ramona Company has the following labor-related data. Standard labor hours for output: 15,000 hours Standard labor rate: $10 per hour Actual labor rate: $8 per hour Actual labor hours: 17,500 hours Given this information, the labor EFFICIENCY variance is

Sagot :

Answer:

$25,000 Unfavourable

Explanation:

The labor Efficiency variance = ( Actual labor Hrs × Standard rate) - ( Standard labor Hr × Standard rate)

= ( 17500 × 10) (15000 × 10)

= 175000 - 150000

= $25,000 Unfavourable

Provided that the standard cost of actual labor hour is greater than the standard labor cost. Then, the variable is unfavorable.