Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

24 men working at 8 hours perday can do a piece of work in 15 day. in how many days can 20 men working at 9 hours day can complete the same work?

Sagot :

Answer:

16 days

Step-by-step explanation:

24 men works 8 hours a day to complete a work in 15 days. While 20 men works at 9 hours per day to complete the same work in x days. We can find the number of days it took the 20 men by using the expression below:

24 men * 8 hours/day * 15 days = 20 men * 9 hours/day * x days

[tex]x (days)=\frac{24\ men * 8\ hours/day * 15\ days }{20\ men * 9\ hours/day} \\\\Simplifying\ gives:\\\\x(days)=16\\\\x=16\ days[/tex]

Therefore it took 20 men working 9 hours/day, 16 days to complete the same work