Westonci.ca is the best place to get answers to your questions, provided by a community of experienced and knowledgeable experts. Get detailed answers to your questions from a community of experts dedicated to providing accurate information. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Answer:
16 days
Step-by-step explanation:
24 men works 8 hours a day to complete a work in 15 days. While 20 men works at 9 hours per day to complete the same work in x days. We can find the number of days it took the 20 men by using the expression below:
24 men * 8 hours/day * 15 days = 20 men * 9 hours/day * x days
[tex]x (days)=\frac{24\ men * 8\ hours/day * 15\ days }{20\ men * 9\ hours/day} \\\\Simplifying\ gives:\\\\x(days)=16\\\\x=16\ days[/tex]
Therefore it took 20 men working 9 hours/day, 16 days to complete the same work
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.