Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Join our Q&A platform and connect with professionals ready to provide precise answers to your questions in various areas. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.

a. more than 10 but less than or equal to 20 days
b. more than 20 but less than or equal to 30 days
c. more than 30 but less than or equal to 40 days
d. more than 40 days


Sagot :

Answer:

a. more than 10 but less than or equal to 20 days

Explanation:

The earliest due date is most popularly known as the EDD rule in the industry. It is defined as the rule that gives the job with an earliest due date which is based on the assigned due dates to the highest priority. These rules are applied by the workers who specializes in the low volume production to medium volume production. It also utilizes batch processes or job processes.

Using the EDD or earliest due date rule, an average flow time for 5 jobs should be more  than ten days but it should be less than twenty days or equal to twenty days.