Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Join our platform to connect with experts ready to provide precise answers to your questions in different areas. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

In January, Dieker Company requisitions raw materials for production as follows: Job 1 $950, Job 2 $1,460, Job 3 $710, and general factory use $610. During January, time tickets show that the factory labor of $6,800 was used as follows: Job 1 $2,300, Job 2 $1,800, Job 3 $1,590, and general factory use $1,110.

Required:
Prepare the job cost sheets for each of the three jobs.

Sagot :

Answer:

Cost of Job 1

Materials $ 950

Factory Labor $ 2300

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4970

Cost of Job 2

Materials $ 1460

Factory Labor $ 1800

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4980

Cost of Job 3

Materials $ 710

Factory Labor $ 1590

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4020

Explanation:

Preparation for the job cost sheets for each of the three jobs.

JOB COST SHEETS

Job1 Job2 Job 3

Materials $950 $ 1460 $710

Factory Labor $2300 $ 1800 $1590

General Factory

Indirect material $ 610 $ 610 $610

Indirect labor $ 1110 $ 1110 $1110

Total $4970 $4980 $4020

Cost of Job 1

Materials $ 950

Factory Labor $ 2300

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4970

Cost of Job 2

Materials $ 1460

Factory Labor $ 1800

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4980

Cost of Job 3

Materials $ 710

Factory Labor $ 1590

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4020

Therefore the job cost sheets for each of the three jobs will be:

Cost of Job 1

Materials $ 950

Factory Labor $ 2300

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4970

Cost of Job 2

Materials $ 1460

Factory Labor $ 1800

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4980

Cost of Job 3

Materials $ 710

Factory Labor $ 1590

General Factory:

Indirect material $ 610

Indirect labor $ 1110

Total $ 4020

Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.