At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Discover reliable solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer:
[Debit] Work In Process : Assembly Department $47,064
[Debit] Work In Process : Finishing Department $19,504
[Credit] Overheads $66,568
Explanation:
Note that overheads are assigned to departments on the basis of 160% of labor costs. Thus, our first point of call is to determine the labor cost for the respective departments. After that we then apply the 160 % to arrive at the Overheads assigned to that department
Step 1
Determine Departmental Labor Cost
Total Labor Costs = $62,800
Assembly Department = ( $44,400)
Finishing Department = $18,400
Step 2
Determine Overhead Cost for the Departments
Assembly Department ( $44,400 × 160 %) = $47,064
Finishing Department ( $18,400 × 160 %) = $19,504
Step 3
Journalize
Debit the Work In Process Account for the respective department and Credit the Overheads Account as above.
Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.