Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

Describe the triple constraint. What are the three components and what is the relationship between them

Sagot :

Answer:

The triple constraint represents the three constraints or inputs which control the project's capacity to produce.

The three components are Budget, time, and scope.

The relationship between them is an interdependent or triangular shape.

Step-by-step explanation:

The triple constraint represents the three constraints or inputs which control the project's capacity to produce. Budget, Scope and Time.

  • Budget - The budget describes the estimated cost of the project.
  • Time: The time represents the deadline to complete the project.
  • Scope: This is simply what needs to be provided.

These 3 components are dependent to each other.

For example, if time is restricted then scope and budget will be affected. similarly.

The relationship between the three is that one of the two other components must decrease while one component increases for the project to succeed as expected.