Westonci.ca is the ultimate Q&A platform, offering detailed and reliable answers from a knowledgeable community. Ask your questions and receive detailed answers from professionals with extensive experience in various fields. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

You work on a concrete crew starting a construction project. Once the pouring begins, it must continue non-stop until it is completed. Your crew will work an 8-hour shift along with two other crews. The total project requires 175,000 yards of concrete. Your supervisor estimates that each crew will pour around 1200 yards per hour. How many consecutive days should you plan to work on this project? A3 B.6 C. 18 D. 27

I need to know the explanation on how to find the answer out as well, please and thank you.