At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Our platform provides a seamless experience for finding reliable answers from a knowledgeable network of professionals. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

at the end of 2018, river plate builders had two jobs still in process with a total balance of $132,200. what overhead rate is river plate using

Sagot :

Answer: d. 80% of direct material cost

Explanation:

Overhead cost = Total costs - Direct material - Direct labor

= 132,200 - 25,000 - 32,000 - 12,500 - 17,100

= $45,600

Direct materials cost = 32,000 + 25,000

= $57,000

Percentage of Direct materials = Overhead/ Direct materials

= 45,600/57,000

= 80%