Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

at the end of 2018, river plate builders had two jobs still in process with a total balance of $132,200. what overhead rate is river plate using

Sagot :

Answer: d. 80% of direct material cost

Explanation:

Overhead cost = Total costs - Direct material - Direct labor

= 132,200 - 25,000 - 32,000 - 12,500 - 17,100

= $45,600

Direct materials cost = 32,000 + 25,000

= $57,000

Percentage of Direct materials = Overhead/ Direct materials

= 45,600/57,000

= 80%