At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Get immediate and reliable answers to your questions from a community of experienced experts on our platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to prepare an aggregate plan for the next six months using the following information.
MONTH
1 2 3 4 5 6
Demand 160 150 160 180 170 140
Capacity
Regular 150 150 150 150 160 160
Overtime 10 10 0 10 10 10
Cost Per Unit
Regular time $58
Overtime 74
Sub-contract 81
Inventory, per period 4
Sub-contracting can handle a maximum of 10 units per month. Beginning inventory is zero. Develop a plan that minimizes total cost. No back orders are allowed.
Period 1 2 3 4 5 6 Total
160 150 160 180 170 140 960
150 150 150 150 160 140 900
Overtime 10 10 0 10 10 0 40