Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

Assume that it takes an average of 3 man-hours to stack 1 ton of a particular item. In order to stack 36 tons in 6 hours, the number of people required is:______.
A) 9
B) 12
C) 15
D) 18
E) 21


Sagot :

Answer:

option (d)

Explanation:

Given,

1 ton of a particular item can be stack in= 3 man-hours

36 ton of a particular item can be stack in=  36 x 3 man-hours

                                                                     = 108man- hours

Number of hours = 6 hours

Number of people = [tex]\frac{108 \text{man-hours}}{6}[/tex]

                               = 18

Hence, the number of people required is 18.

Therefore, option (d) is correct.