Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.
Sagot :
Answer:
a. Materials, 100%; labor, 100%; overhead cost, 40%.
Explanation:
The work in Process have already passed the mark at which Materials and Labor are added, that is the start of its production process so these are both 100% complete. Overheads are 40 % complete, which is the extent of work done on them since they occur evenly.
Thank you for choosing our service. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.