Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Explore a wealth of knowledge from professionals across various disciplines on our comprehensive Q&A platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

A construction manager needs 12 workers to complete a building project in 54 days. Find in terms of T the number of workers needed to complete the same project in T days

Sagot :

Answer:

2T/9

Step-by-step explanation:

A construction manager needs 12 workers to complete a building project in 54 days, we can write;

12 workers = 54 days

T find the number of workers needed to complete the same project in T days, we will write;

x workers = T days

Divide both equations

12/x = 54/T

Cross multiply

12T = 54x

x = 12T/54

x = 2T/9

Hence the number of workers needed to complete the same project in T days is 2T/9 workers

Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.