Westonci.ca is the premier destination for reliable answers to your questions, brought to you by a community of experts. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

Reamer Company uses a predetermined overhead rate based on machine hours to apply manufacturing overhead to jobs. The company has provided the following estimated costs for the next year: Direct materials - $1000, Direct labor - $3000, Sales commissions - $4000, Salary of production supervisor - $2000, Indirect materials - $400, Advertising expense - $800, Rent on factory equipment - $1000. Reamer estimates that 500 direct labor hours and 1000 machine hours will be worked during the year. The predetermined overhead rate per hour will be:__________
A. $6.80
B. $6.00
C. $3.00
D. $3.40


Sagot :

Answer:

D. $3.40

Explanation:

The computation of the predetermined overhead rate is shown below:

Predetermined overhead rate is

= Estimated manufacturing overhead ÷ estimated machine hours

= ($2,000 + $400 + $1,000) ÷ (1,000 machine hours)

= $3,400 ÷ $1,000 machine hours

= $3.40 per hour

We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.