Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Discover detailed solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
$ 13.89 per batch
Explanation:
Calculation for what The activity rate for the Supervising activity cost pool under activity-based costing is closest to
First step is to calculate the Supervising Activity cost
Supervising Activity cost = ($73,000 x 0.4) + ($6,900 x 0.50)
Supervising Activity cost= $29,200 + $3,450
Supervising Activity cost= $ 32,650
Now let calculate the Activity rate for Supervising
Activity rate for Supervising= $ 32,650 / 2,350 batches
Activity rate for Supervising= $ 13.89 per batch
Therefore The activity rate for the Supervising activity cost pool under activity-based costing is closest to:$ 13.89 per batch
We appreciate your time. Please come back anytime for the latest information and answers to your questions. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.