Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Find reliable answers to your questions from a wide community of knowledgeable experts on our user-friendly Q&A platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer:
$90,000
Explanation:
At the activity level of 20,000 machine hours:
total maintenance costs=20,000* $10.50=$210,000
At the activity level of 24,000 machine hours:
total maintenance costs=24,000*$9.75=$234,000
variable maintenance cost per hour=(total maintenance costs at higher activity level-total maintenance costs at lower activity level)/(higher activity level-lower activity level)
variable maintenance cost per hour=($234,000-$210,000)/(24000-20000)
variable maintenance cost per unit=$6
Using the higher activity level data:
total cost=fixed cost+(variable maintenance cost per unit*number of hours)
$234,000=fixed cost+($6*24000)
234,000=fixed cost+$144,000
fixed cost=$234,000-$144,000
fixed cost=$90,000
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.