Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Connect with professionals ready to provide precise answers to your questions on our comprehensive Q&A platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

At Medallion Industries, variable cost per unit is budgeted to be $8.00 and fixed cost per unit is budgeted to be $5.00 in a period when 4,000 units are produced. What is the expected total cost of the units produced at Medallion, if instead, production is actually 5,100 units

Sagot :

Answer:

Total cost= $60,800

Explanation:

Giving the following information:

For 4,000 units:

Unitary variable cost= $8

Unitary fixed cost= $5

First, we need to calculate the total fixed cost:

Total fixed cost= 5*4,000= $20,000

Now, we can determine the total cost for 5,100 units:

Total cost= 5,100*8 + 20,000

Total cost= $60,800