Discover a wealth of knowledge at Westonci.ca, where experts provide answers to your most pressing questions. Ask your questions and receive accurate answers from professionals with extensive experience in various fields on our platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

At Medallion Industries, variable cost per unit is budgeted to be $8.00 and fixed cost per unit is budgeted to be $5.00 in a period when 4,000 units are produced. What is the expected total cost of the units produced at Medallion, if instead, production is actually 5,100 units

Sagot :

Answer:

Total cost= $60,800

Explanation:

Giving the following information:

For 4,000 units:

Unitary variable cost= $8

Unitary fixed cost= $5

First, we need to calculate the total fixed cost:

Total fixed cost= 5*4,000= $20,000

Now, we can determine the total cost for 5,100 units:

Total cost= 5,100*8 + 20,000

Total cost= $60,800