Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Discover comprehensive answers to your questions from knowledgeable professionals on our user-friendly platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Complete question :
Insulated concrete forms (ICF) can be used as a substitute for conventional wood framing in building construction. Heating and cooling bills will be about 60% less than in a similar wood-framed building in upstate New York. An ICF home will be approximately 10% more expensive to construct than a wood-framed home. For a typical 1,800 ftsquared2 home costing $130 ftsquared2 to construct in upstate New York and costing $260 per month to heat and cool, how many months does it take for a 1,800 ftsquared2 ICF home to pay back its extra construction cost?
Answer:
150 months
Step-by-step explanation:
Wood framing Construction cost :
Cost per ft² = $130
Total cost for 1800 ft² :
1800 * $130 = $234,000
Heating and cooling cost = $260
An ICF home:
Construction cost will be approximately 10% more expensive :
Hence, total cost of ICF = (1.1) * 234000 = $257,400
Extra cost on construction :
$257,400 - $234000 = $23,400
Heating and cooling cost ; 60% less expensive = (1 - 0.6) * $260 = $104
Saving in heating and cooling = $260 - $104 = $156 monthly
Number of months it takes to pay extra cost on construction :
Extra cost on construction / saving in heating & cooling
= $23,400 / $156
= 150 months
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.