At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Get quick and reliable solutions to your questions from a community of experienced professionals on our platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
$5,160
Explanation:
Predetermined Overhead Rate on Capacity = Total Estimated Manufacturing Overhead / Estimated Capacity for the Year
Predetermined Overhead Rate on Capacity = $34,840 / 29,000 MH
Predetermined Overhead Rate on Capacity = $1.20 MH
Actual use of capacity = 24,700 hours
Unused hours = 29,000 hours - 24,700 hours
Unused hours = 4,300 hour
Cost of unused capacity = 4,300 hours * $1.20 MH
Cost of unused capacity = $5,160
Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.