Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Explore in-depth answers to your questions from a knowledgeable community of experts across different fields. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

How you find the applied overhead

Sagot :

Answer:

Multiply the overhead allocation rate by the actual activity level to get the applied overhead for your cost object. If your overhead allocation rate is $100 per machine hour, then multiply $100 times the number of machine hours for a particular product to get its applied overhead.