Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Discover precise answers to your questions from a wide range of experts on our user-friendly Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Problem 3.10 One/half million parts of a certain type are to be manufactured annually on dedicated production machines that run 16 hours per day, five days per week, 50 weeks per year. (a) The cycle time to produce one part is 1.8 min. If availability and utilization are each 100%, and setup time is neglected, how many of the machines will be required to satisfy demand? (b) Solve part (a) except that availability = 95%.

Sagot :

Answer:

  • 4 machines
  • 4 machines

Explanation:

(a) The production schedule is 4000 hour per year, or 240,000 minutes. In that time, 133,333 1/3 parts can be produced. The production of 500,000 parts in a year will require the use of ...

  .5 million/(.1333... million/machine) = 3.75 machines

The demand can be satisfied by 4 machines.

__

(b) If availability is 95% then 3.75/0.95 ≈ 3.95 machines will be required.

The demand can be satisfied by 4 machines.

Answer:

  • 4 machines
  • 4 machines

A.

B

are both in 4 machines used in