Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Discover detailed solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

Problem 3.10 One/half million parts of a certain type are to be manufactured annually on dedicated production machines that run 16 hours per day, five days per week, 50 weeks per year. (a) The cycle time to produce one part is 1.8 min. If availability and utilization are each 100%, and setup time is neglected, how many of the machines will be required to satisfy demand? (b) Solve part (a) except that availability = 95%.

Sagot :

Answer:

  • 4 machines
  • 4 machines

Explanation:

(a) The production schedule is 4000 hour per year, or 240,000 minutes. In that time, 133,333 1/3 parts can be produced. The production of 500,000 parts in a year will require the use of ...

  .5 million/(.1333... million/machine) = 3.75 machines

The demand can be satisfied by 4 machines.

__

(b) If availability is 95% then 3.75/0.95 ≈ 3.95 machines will be required.

The demand can be satisfied by 4 machines.