Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Discover the answers you need from a community of experts ready to help you with their knowledge and experience in various fields. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Help pls! If one front-loader operator can dig 6 cubic yards of dirt per minute, how many hours
would it take two front-loader operators working together at the same rate to dig a snow
making a trench that requires removal of 3250 cubic yards of dirt?


Sagot :

Answer:

4.51389

Step-by-step explanation:

6*2=12 yd³/min

12*60= 720 yd³/hour

3250÷ 720 yd³/hour = 4.51389 hours

4.51389