At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

Jackson Inc. listed the following data for 2019: Budgeted factory overhead $1,272,000 Budgeted direct labor hours 80,000 Budgeted machine hours 40,000 Actual factory overhead 1,201,400 Actual direct labor hours 86,700 Actual machine hours 39,800 Assuming Jackson Inc. applied overhead based on machine hours, the firm's predetermined overhead rate for 2019 (round calculations to 2 significant digits) is:

Sagot :

Answer: $31.80 per machine hour

Explanation:

Based on the information that have been given in the question, since the overhead was applied by Jackson Inc., therefore, the firm's predetermined overhead rate will be:

= Budgeted factory overhead / Budgeted machine hours

= $1,272,000 / 40000

= $31.80 per machine hour

Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.