Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Ask your questions and receive detailed answers from professionals with extensive experience in various fields. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Answer:
hello your question is incomplete attached below is the complete question
answer : attached below
Explanation:
A) develop the from-to chart based on expected weekly production
Firstly we calculate the production quantity processed
i) Qab = 960 + 1200 + 720 + 2400 + 480 + 2400 + 3000 + 960 + 1200 = 13320
ii) Qbd = 2400 + 3000 + 1200 = 6600
B) calculate the values to be entered in cells of table attached below (develop a block layout using SLP )
Cell bc = 11400 + 6600 = 18000
Cell bd = 6600 + 3000 = 9600
Cell be = 4920 + 5400 = 10320
Cell cd = 2400 + 1200 = 3600
Cell ce = 4200 + 7800 = 12000
Cell df = 960 + 1200 = 2160
Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.