Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Ask your questions and receive detailed answers from professionals with extensive experience in various fields. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

XYZ Inc. has a facility with six departments (A, B, C, D, E, and F). A summary of the processing sequence for 10 products and the weekly production forecasts for the products are given in the tables below. a. Develop the from-to chart based on the expected weekly production. b. Develop a block layout using SL

Sagot :

Answer:

hello your question is incomplete attached below is the complete question

answer : attached below

Explanation:

A) develop the from-to chart based on expected weekly production

Firstly we calculate the production quantity processed

i) Qab = 960 + 1200 + 720 + 2400 + 480 + 2400 + 3000 + 960 + 1200 = 13320

ii) Qbd = 2400 + 3000 + 1200 = 6600

B) calculate the values to be entered in cells of table attached below (develop a block layout using SLP )

Cell bc = 11400 + 6600 = 18000

Cell bd = 6600 + 3000 = 9600

Cell be = 4920 + 5400 = 10320

Cell cd = 2400 + 1200 = 3600

Cell ce = 4200 + 7800 = 12000

Cell df = 960 + 1200 = 2160

View image batolisis
View image batolisis
View image batolisis