Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
Answer:
The IRS's claim (that the average time it takes to complete a project is < 6 months) is wrong. It takes the Department 23.52 months to complete a project.
Explanation:
a) Data and Calculations:
Number of projects "on the Department’s plate" (I) = 588 Projects
Average projects completed per year (R) = 300 Projects
Therefore, the flow time (the average time to complete a project by the department), T, = I / R
= 588 / 300 = 1.96 years = 1.96 X 12 = 23.52 months
b) The steps to calculate flow time (the amount of time a flow unit spends in a business process from beginning to end) are given as:
1. The number of projects handled over a period of time.
2. Let R = the number of units produced / duration of time period .
3. Compute the average inventory (I).
4. Compute flow time T =I/R.
Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.