Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Get immediate and reliable solutions to your questions from a knowledgeable community of professionals on our platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer: Hope this help. Please mark me brainliest :)
Explanation:
a.
Before: 90 ÷ 6 = 15.00 carts per worker per hour.
After: 96 ÷ 5 = 19.20 carts per worker per hour.
b.
Before: $14 x 6 = $84 + $40 = $124; hence 90 ÷ $124 = 0.73 carts/dollar cost.
After: $14 x 5 = $70 + $51 = $121; hence 96 ÷ $121 = 0.79 carts/dollar cost.
c.
Labor productivity increased by 28.00% (4.20/15.00).
Multifactor productivity increased by 8.22% (0.06/0.73).
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.