Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Get expert answers to your questions quickly and accurately from our dedicated community of professionals. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

How many workers will be needed to complete a task in 6 days, given that it takes 8 days for 3 workers to complete the same task?

Sagot :

Answer:

4

Step-by-step explanation:

8*3 = 24

24/6 = 4