Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Discover the answers you need from a community of experts ready to help you with their knowledge and experience in various fields. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

Consider a four-step serial process with processing times given in the list below. There is one machine at each step of the process and this is a machine-paced process.

Step 1: 26 minutes per unit
Step 2: 16 minutes per unit
Step 3: 23 minutes per unit
Step 4: 26 minutes per unit

Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 91 units?

Sagot :

Answer:

40.22 hours

Explanation:

The computation of the time taken as follows:

= 26 minutes × 91 units

= 2,366

In hours

= 2,366 ÷ 60 minutes

= 39.43

The total time taken for machine step is

= 16 + 23

= 39 minutes

So, the total time taken is

= 39.43 + 39 minutes

= 40.22 hours

Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.