Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Discover a wealth of knowledge from experts across different disciplines on our comprehensive Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

Playtime Industries manufactures custom-designed playground equipment for schools and city parks. Playtime expected to incur $664,000 of manufacturing overhead cost, 41,500 of direct labor hours, and $830,000 of direct labor cost during the year (the cost of direct labor is $20 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During May, Playtime completed Job 301. The job used 155 direct labor hours and required $12,700 of direct materials. The City of Westlake has contracted to purchase the playground equipment at a price of 20% over manufacturing cost.
Required SHOW WORK
1. Calculate the manufacturing cost of Job 301. (hint: remember you have to consider each product cost: direct materials, direct labor and manufacturing overhead)
2. How much will the City of Westlake pay for this playground equipment?
Playtime Industries manufactures custom-designed playground equipment for schools and city parks. Playtime expected to incur $664,000 of manufacturing overhead cost, 41,500 of direct labor hours, and $830,000 of direct labor cost during the year (the cost of direct labor is $20 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During May, Playtime completed Job 301. The job used 155 direct labor hours and required $12,700 of direct materials. The City of Westlake has contracted to purchase the playground equipment at a price of 20% over manufacturing cost.
Required SHOW WORK
1. Calculate the manufacturing cost of Job 301. (hint: remember you have to consider each product cost: direct materials, direct labor and manufacturing overhead)
2. How much will the City of Westlake pay for this playground equipment?


Sagot :

Answer and Explanation:

The computation is shown below:

1 Calculation of predetermined overhead rate is  

Predetermined overhead rate= Estimated Overhead Cost ÷  Direct labor hours

= $664,000 ÷ 41,500

= $16 per direct labor hour.

Now

Calculation of Total Job Cost:-

Direct Materials $12,700

Direct Labor            $3,100

(155 direct labor hours × $20 per hour)  

Manufacturing Overhead $2,480  

(155 direct labor hours × $16 per hour)

 Total Job Cost $18,280

2- Calculation of contracted billing price:-

Total manufacturing cost of Job 301 $18,280

Add: Markup on manufacturing cost  20% of $18,280  $3,656

Billing price $21,936

We hope our answers were useful. Return anytime for more information and answers to any other questions you have. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.