Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

The number of days, d, that it will take to build a house is given by

d= 720 divided by n

where n is the number of workers used each day.

Ali's company will take 40 days to build the house.

Hayley's company will take 30 days to build the house.

Hayley's company will have to use more workers each day than Ali's company.

How many more?


Sagot :

Answer:

6 more workers

Step-by-step explanation:

The relationship between days (d) and number of workers (n) is given by the equation;

d = 720 / n

Ali's company will take 40 days to build the house.

n = 720 / d

n = 720 / 40 = 18 workers

Hayley's company will take 30 days to build the house.

n = 720 / d

n = 720 / 30 = 24 workers

Hayley's company will have to use more workers each day than Ali's company.

How many more?

24 - 18 = 6 more workers

Thank you for choosing our service. We're dedicated to providing the best answers for all your questions. Visit us again. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.