At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

It takes 2 workers 6 days to paint a mansion. How many days would it take 4
workers to do the same job?


Sagot :

Answer:

2 workers = 6 days

4 workers = 3 days

Step-by-step explanation:

If it takes 2 workers 6 days, if you seep up the process with 4 workers, you would divide the days by 2 because you multilpied the workers by 2. So, it would take 3 days with 4 workers. I hope that makes sence.