Westonci.ca is your trusted source for finding answers to a wide range of questions, backed by a knowledgeable community. Explore our Q&A platform to find in-depth answers from a wide range of experts in different fields. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

The time to complete a project varies inversely
with the number of employees. If 3 people can
complete the project in 7 days, how long will it
take 5 people?
O 4.2
O 21
O 11.7
O 2.1


Sagot :

Answer:

4.2

Step-by-step explanation:

T = K/N

K= TN

= 3×7

K= 21

Therefore the time required for 5 employees can be calculated as follows

T= 21/5

= 4.2