Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Discover comprehensive answers to your questions from knowledgeable professionals on our user-friendly platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Answer:
The correct response is "Option a ($19,043)"
Explanation:
The given values are:
Estimated overhead,
= $33,075
Sales,
= $79,268
Estimated shaper hours,
= 270 hours
Direct materials,
= $12,200
Direct labor,
= $17,400
Actual shaper hours,
= 250 hours
Now,
The fixed overhead rate will be:
= [tex]\frac{Estimated \ overhead}{Estimated \ Shaper \ hours}[/tex]
On substituting the values, we get
= [tex]\frac{33,075}{270}[/tex]
= [tex]122.50 \ per \ shaper[/tex] ($)
The applied fixed overhead will be:
= [tex]Actual \ shaper \ hours\times Fixed \ overhead \ rate[/tex]
= [tex]250\times 122.50[/tex]
= [tex]30,625[/tex] ($)
then,
The total cost of sold goods will be:
= [tex]Direct \ materials +Direct \ labor +Applied \ overhead \[/tex]
= [tex]12,200+ 17,400+ 30,625[/tex]
= [tex]60,225[/tex] ($)
The gross margin will be:
= [tex]Sales-Cost \ of \ goods \ sold[/tex]
On substituting the above given values, we get
= [tex]79,268-60,225[/tex]
= [tex]19,043[/tex] ($)
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for choosing Westonci.ca as your information source. We look forward to your next visit.