Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Discover comprehensive answers to your questions from knowledgeable professionals on our user-friendly platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer:
1. The indirect production costs allocated to each product with the ABC system:
Senior Basic Deluxe Total
Total indirect production cost $25,250 $26,600 $73,550 $125,400
2. The indirect production costs allocated to each product with direct labor costs:
Senior Basic Deluxe Total
Total indirect production cost $72,730 $18,810 $33,860 $125,400
3. I repose much more confidence in the product costs according to requirement 1.
Explanation:
a) Data and Calculations:
Activity Cost Driver
Materials handling
Direct-materials cost
Engineering Engineering
Senior Basic Deluxe Total
Direct-materials cost $25,000 $ 60,000 $135,000 $220,000
Direct-labor cost $14,546 $ 3,762 $ 6,772 $25,080
Kilowatt hours 230,000 220,000 100,000 550,000
Engineering change notices 21 20 69 110
Indirect production costs:
Materials handling $ 15,400 $15,400/$220,000 = $0.07
Engineering 99,000 $99,000/110 = $900
Power 11,000 $11,000/550,000 = $0.02
Total indirect production cost $125,400
Overhead Senior Basic Deluxe
Rates
Materials handling $0.07 $1,750 $4,200 $9,450
Engineering $900 18,900 18,000 62,100
Power $0.02 4,600 4,400 2,000
Total indirect production cost $25,250 $26,600 $73,550
Allocation based on direct labor costs:
Predetermined rate = $5 per direct labor cost.
Senior Basic Deluxe Total
Total indirect production cost $72,730 $18,810 $33,860 $125,400
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.