Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Join our Q&A platform to connect with experts dedicated to providing precise answers to your questions in different areas. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.
Sagot :
Answer:
Results are below.
Explanation:
First, we need to calculate the predetermined plantwide overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
total estimated overhead costs for the period= $1,320,000
total amount of allocation base= 100,000
Predetermined manufacturing overhead rate= 1,320,000 / 100,000
Predetermined manufacturing overhead rate= $13.2 per direct labor hour
Now, we can allocate overhead to each product line:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Part A27C:
Allocated MOH= 13.2*(5,500 + 700)
Allocated MOH= $81,840
Part X82B:
Allocated MOH= 13.2*(2,150 + 3,500)
Allocated MOH= $74,580
Thank you for your visit. We are dedicated to helping you find the information you need, whenever you need it. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.