Explore Westonci.ca, the top Q&A platform where your questions are answered by professionals and enthusiasts alike. Explore our Q&A platform to find in-depth answers from a wide range of experts in different fields. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
3 hours
Step-by-step explanation:
Let the number of cleaners be x
Let the time taken be y
This relationship is inverse
x = k/y
If x = 3 and y = 4
3 = k/4
k = 3*4
k = 12
To get the time it will take 4 people, we will substitute k = 12 and x = 4 into the expression x = k/y
x = 12/4
x = 3
Hence it will take 4 people 3 hours at the same rate
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.