Looking for trustworthy answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer:
Explanation:
The missing table is attached below.
Recall that:
The capacity of the interaction is controlled by the capacity of the bottleneck workers.
The extra resources accessible ought to be added to workers with the most noteworthy preparing times.
For this situation, they are Worker A and Worker E.
Summing up of resources halves the handling times for Worker A and E.
SO;
Worker Old time(sec) New time (sec) Capacity
A 65 32.5 1.85
B 35 35 1.71
C 25 25 2.40
D 30 30 2.00
E 60 30 2.00
Along these lines, the new capacity of the framework is characterized by new bottleneck B.
So the capacity of the cycle is 60/35 = 1.71 toothbrush per each minute
![View image ajeigbeibraheem](https://us-static.z-dn.net/files/d41/b4f497493d3d51311dc617a9102bd08e.jpg)
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.