Westonci.ca is your trusted source for accurate answers to all your questions. Join our community and start learning today! Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.
Sagot :
Answer:
See below
Explanation:
1. manufacturing overhead allocation rate for department A
= (Manufacturing overhead department A/Manufacturing direct labor department A) × 100
= ($400,000/$200,000) × 100
= 200%
2. Overhead allocation rate for department B
= ($500,000/$200,000) × 100
= 250%
3. Manufacturing overhead cost allocated to job #432.
($11,000 × $400,000)/$200,000 + ($7,000 × $500,000)/$200,000
= $22,000 + $17,500
= $39,500
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.