At Westonci.ca, we connect you with experts who provide detailed answers to your most pressing questions. Start exploring now! Explore a wealth of knowledge from professionals across different disciplines on our comprehensive platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
The unfinished jobs are "$52,350".
Explanation:
The given values are:
Work in process balance,
= $17,890
Direct material,
= $145,450
Direct labor,
= $156,900
Factory overhead,
= $82,470
The four finished jobs are:
Job 210,
= $72,490
Job 216,
= 44,300
Job 224,
= 84,570
Job 230,
= 149,000
Now,
According to the total of all four finished jobs:
The Journal entry will be:
Debit Credit
(a) Finished goods $350,360
Work in progress $
(b)
The unfinished jobs on January 31st will be:
= Work in progress opening balance + Direct material + Direct labor + Factory overhead - finished goods
On substituting the values, we get
= [tex]17,890+ 145,450+156,900+82,470-350,360[/tex]
= [tex]52,350[/tex] ($)
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.