Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

The WBS is an input for which of the following activities?
A.
Schedule planning and budget planning
B.
Schedule planning and scope planning
MARKET
C. Budget planning and project charter creation
D.
Scope planning and budget planning
Is ?


Sagot :

Lanuel

Answer:

A. Schedule planning and budget planning.

Explanation:

Work Breakdown Structure (WBS) is a tool that the project manager uses to progressively divide deliverables into smaller pieces. It gives framework that can be used as a basis for further planning activities. They are displayed in an indented outline format.

Simply stated, Work Breakdown Structure (WBS) in project management is the laser-focused breakdown of a project into smaller components in order to make the project successful.

Hence, the WBS is an input for schedule planning and budget planning.

This ultimately implies that, the WBS is the starting place for schedule planning and budget (financial) planning, and as a result, it serves as the critical input to various deliverables and processes in project management.