Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

The WBS is an input for which of the following activities?
A.
Schedule planning and budget planning
B.
Schedule planning and scope planning
MARKET
C. Budget planning and project charter creation
D.
Scope planning and budget planning
Is ?


Sagot :

Lanuel

Answer:

A. Schedule planning and budget planning.

Explanation:

Work Breakdown Structure (WBS) is a tool that the project manager uses to progressively divide deliverables into smaller pieces. It gives framework that can be used as a basis for further planning activities. They are displayed in an indented outline format.

Simply stated, Work Breakdown Structure (WBS) in project management is the laser-focused breakdown of a project into smaller components in order to make the project successful.

Hence, the WBS is an input for schedule planning and budget planning.

This ultimately implies that, the WBS is the starting place for schedule planning and budget (financial) planning, and as a result, it serves as the critical input to various deliverables and processes in project management.