Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Connect with a community of experts ready to provide precise solutions to your questions quickly and accurately. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer:
a. Station Staffing Processing time Capacity
(hours/chair/worker) (Staffing/activity time)
Stripping 3 workers 2.5 3/2.5 = 1.2
Priming 2 workers 1.5 2/1.5=1.33
Painting 2 workers 1.75 2/1.75=1.14
Inspection 1 worker 17/10=1.7 1/1.7=0.59
Inspection have the bottle neck, due to the least capacity (0.59). So, the process capacity can be given as 0.59
Total time to produce first chair =2.5+1.5+1.75+1.7 = 7.45 hours
Total time to make the each subsequent chair will be 1/0.59
b. So, total time to complete 15 chairs = (7.45)+ (1/0.59)*14
= 7.45 + 23.73
= 31.18 hours
c. In this case, there will be no bottle neck as each worker will be operating with its full capacity.
Total time taken by each worker to finish one chair = 2.5+1.5+1.75+1.7 = 7.45 hours & Total workers = 8
Maximum capacity = 8/7.45
Maximum capacity = 1.074 chairs per hour
Thank you for choosing our service. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.