Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
a. Station Staffing Processing time Capacity
(hours/chair/worker) (Staffing/activity time)
Stripping 3 workers 2.5 3/2.5 = 1.2
Priming 2 workers 1.5 2/1.5=1.33
Painting 2 workers 1.75 2/1.75=1.14
Inspection 1 worker 17/10=1.7 1/1.7=0.59
Inspection have the bottle neck, due to the least capacity (0.59). So, the process capacity can be given as 0.59
Total time to produce first chair =2.5+1.5+1.75+1.7 = 7.45 hours
Total time to make the each subsequent chair will be 1/0.59
b. So, total time to complete 15 chairs = (7.45)+ (1/0.59)*14
= 7.45 + 23.73
= 31.18 hours
c. In this case, there will be no bottle neck as each worker will be operating with its full capacity.
Total time taken by each worker to finish one chair = 2.5+1.5+1.75+1.7 = 7.45 hours & Total workers = 8
Maximum capacity = 8/7.45
Maximum capacity = 1.074 chairs per hour
We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.