Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Get immediate and reliable solutions to your questions from a community of experienced experts on our Q&A platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer:
1. A. 315,550 or more
2. B. B
Explanation:
Number of boats is 115
Alternative A :
New location cost are
Fixed cost $250,000
Transportation cost increase is $5200
Variable cost is $700 per boat
Total cost per boat is (250,000 + 5200 ) / 115 + 700 = 2,919 per boat.
Alternative B :
Subcontract costs are
Transportation cost increase is $28,000
cost per boat is $3,100 per boat
Total cost per boat is 28,000 / 115 + 3,100 = 3,343 per boat.
Alternative C :
New location cost are
Fixed cost $60,000
Transportation cost increase is $81,000
Variable cost is $1,700 per boat
Total cost per boat is (60,000 + 81,000 ) / 115 + 1,700 = 2,926 per boat.
Best alternative is A ( New Location ) which results in lowest total cost per boat.