Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

As a financial analyst, you are tasked with evaluating a capital-budgeting project. You were instructed to use the IRR method, and you need to determine an appropriate hurdle rate. The risk-free rate is 4%, and the expected market rate of return is 11%. Your company has a beta of 0.67, and the project that you are evaluating is considered to have risk equal to the average project that the company has accepted in the past.According to CAPM, the appropriate hurdle rate would be:_______.
A) 4%.
B) 8.69%.
C) 15%.
D) 11%.
E) 0.75%.


Sagot :

Answer:

B) 8.69%.

Explanation:

Calculation for what the appropriate hurdle rate would be:

Hurdle rate= 4% + 0.67(11% - 4%)

Hurdle rate = 4% + 0.67*0.07

Hurdle rate=4%+0.0469

Hurdle rate=0.0869*100

Hurdle rate=8.69%