Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Discover comprehensive solutions to your questions from a wide network of experts on our user-friendly platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer:
Unitary total cost= $123.74
Explanation:
First, we need to calculate the activities rates to allocate costs:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Assembly= 926,800/56,000= $16.55 per machine-hour
Processing orders= 68,310 / 1,800= $37.95 per order
Inspection= 103,360 / 1,360= $76 per inspection-hour
Now, we can allocate costs based on actual activity:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Assembly= 16.55*1,060= 17,543
Processing orders= 37.95*80= 3,036
Inspection= 76*20= 1,520
Total allocated costs= $22,099
Unitary allocated costs= 22,099/700= $31.57
Finally, the unitary total cost:
Unitary total cost= 31.57 + 51 + 41.17
Unitary total cost= $123.74
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.